Minister za infrastrukturo in energetiko Jernej Vrtovec si je zvečer v spremstvu predstavnikov družbe Dars ogledal potek obnovitvenih del na odseku primorske avtoceste med Ravbarkomando in Postojno, ki je z velikim številom nesreč sprožalo največ negodovanja med vozniki. "Nocoj se na avtocesti pri Postojni začenja nočno delo," je Vrtovec že čez dan napovedal na Facebooku.
V oddaji 24UR ZVEČER je Vrtovec na vprašanje, kaj je bilo treba storiti, da so se danes ponoči začela dela na gradbišču pri Postojni, odgovoril: "Samo ena stvar – in to je volja."
Spomnil je, da so v koalicijski pogodbi zapisali, da bo poleg cene v razpisih eden ključnih pogojev tudi rok izvedbe del. "Če želijo biti naši gradbeni izvajalci konkurenčni, potem morajo poprijet za delo in gradit tudi ponoči. In tukaj ni heca, zato ker če ljudje ure in ure čakajo v zastojih, potem je logično, da moramo tudi na drugi strani prilagodit vse stvari temu in tudi razpise, da je to čakanje v zastojih poplačano, da je časovna izvedba čim krajša. Gradbeni izvajalci so pripravljeni na delo ponoči, ne samo pri Postojni, ampak tudi drugje," je dejal Vrtovec.
Po ministrovih besedah, se bo zaradi nočnega dela dokončanje del skrajšalo za približno 20 do 30 dni. "Torej skoraj en mesec bomo zaradi nočnih del pridobili in bo to delovišče prej odprto, s tem pa tudi manj prometnih nesreč, sproščen promet in tako dalje," je zatrdil.
Dela naj bi od zdaj naprej torej tekla ves čas, podnevi in se nadaljevala v noč, torej brez prekinitev, vse dokler se dela ne zaključijo - tako vsaj pravi minister Vrtovec, ki je prejšnji teden sicer napovedal, da pričakuje, da začnejo v najkrajšem možnem času ponoči delati tudi drugod, a za zdaj bo prvi pokazatelj, ali zadeva deluje, očitno pri Postojni. Na naša vprašanja Dars in izvajalec del - to je Kolektor CPG - danes niso odgovorili.
Njegova predhodnica Alenka Bratušek je sicer priznala, da bo njegov poskus uvedbe nočnih del na avtocestah spremljala z zanimanjem, saj je sama velikokrat naletela na odpor stroke o delu ponoči, medtem ko je prvi mož Darsa Andrej Ribič maja pojasnjeval, da niso "sposobni včasih spraviti z gradbeniki niti ene izmene, kaj šele dveh ali dela ponoči".
V začetku maja je bila avtocesta med Razdrtim in Postojno zaradi prometne nesreče zaprta skoraj 11 ur. FOTO: Bobo S tem tednom sicer na več odsekih avtocest po državi zaradi vzdrževalnih del velja spremenjena prometna ureditev in zapore. Na Darsu opozarjajo, da so zato možne premične zapore in krajši zastoji. Voznike prosijo za upoštevanje prometne signalizacije in previdno vožnjo skozi območja del.
Primorska avtocesta
Popolna zapora priključka Postojna:
Uvoz proti Ljubljani:
- od ponedeljka, 8. 6. od 17. ure, do sobote, 13. 6. do 5. ure;
- od ponedeljka, 29. 6. od 17. ure za predvidoma 14 dni.
Izvoz iz smeri Kopra:
- od ponedeljka, 22. 6. od 17. ure do predvidoma 12. 7. 2026.
Obvoz bo možen preko priključkov Razdrto in Unec.
Zapore v smeri Ljubljane FOTO: Dars Do predvidoma 31. 8. 2026 bo med Slovenskimi Konjicami in Dramljami promet potekal dvosmerno po vozišču proti Ljubljani, smerno vozišče proti Mariboru bo zaprto.
Slovenske Konjice - Dramlje FOTO: Dars Gorenjska avtocesta
Predvidoma 10. 6. 2026 bodo med Brnikom in Vodicami dela prešla v naslednjo fazo. Promet bo urejen dvosmerno po eni polovici avtoceste.
Od 11. 6. do 18. 6. 2026 bo na priključku Kranj zahod zaprt izvoz iz smeri Jesenic in uvoz proti Ljubljani. Obvoz prek priključka Naklo.
Vipavska hitra cesta
Do predvidoma začetka avgusta 2026 bo med Ajdovščino in Vipavo promet potekal po enem pasu v obe smeri.
Do sredine julija bo zaprt izvoz Ajdovščina iz smeri Nanosa.
Read the full article at 24ur (POP TV) →📄Source document: Minister for Infrastructure and Energy Jernej Vrtovec
5 reports
24ur (POP TV)IndependentCenter4 days ago Reconstruction of the section of the coastal motorway between Kozino and Czarny Kalk completedThe reconstruction of a section of the coastal highway between Kozina and Črni Kal was completed. The project involved the full renovation of roads, facilities, and rest areas in Ravne, with work starting in March of last year and originally scheduled to finish by November. The total length of the road being renovated was 9.9 kilometers, carried out by a consortium of companies including Kolektor CPG, CPK, and GP Krk, with a contract value of 26.6 million euros excluding VAT. Meanwhile, construction continues in the area of Postojna, where night work has recently been introduced. Minister for
Bias read (Center): The article discusses infrastructure development without taking a stance on political issues. It provides factual information about the completion of a highway reconstruction project, mentions the companies involved, and notes ongoing work in another region. There is no indication of ideological slm
Official sources cited
- government Minister for Infrastructure and Energy Jernej Vrtovec
- organisation Company Kolektor CPG
24ur (POP TV)IndependentCenter9 days ago How did the workers get used to the shifts? 'In the current temperatures, it's easier at night'Night work continues on the coastal motorway, including at the construction site near Pivka where workers are building a new bridge. The project is expected to be completed approximately three weeks ahead of schedule due to night shifts. The article asks how workers have adapted to the new shift patterns.
Bias read (Center): The article discusses infrastructure development and labor practices without taking a political stance or showing bias toward any particular ideology. It focuses on factual information about construction progress and worker adaptation to night shifts.
DemokracijaParty-alignedCenter12 days ago (GALERY) The new government is delivering on the coalition pledges: Night work on the coastal highway has begun and continues rapidly throughout the dayThe new government has started night work on sections of the coastal highway where construction and maintenance work cause traffic congestion. Minister Jernej Vrtovec had previously promised that such work would take place at night to minimize disruptions. The work began at the Studenec–Postojna and Postojna–Ravbarkomanda sites, with plans to expand it to other locations. Around 30 workers have been relocated to these areas, and the intensity of night work will increase gradually. Officials estimate that this approach could save between 20 and 30 days overall.
Bias read (Center): The article reports on infrastructure developments without taking a stance on political issues. It focuses on factual updates regarding night work on highways, quoting officials and providing logistical details. There is no evident framing or slant toward any political side.
Official sources cited
- government Statement by Minister Jernej Vrtovec
- organisation Comment by Marko Vihtelič from Kolektor CPG
Maribor24IndependentCenter12 days ago Night work on the highways: Minister Vrtovec wants the reconstruction to be completed as soon as possibleNight work has begun on the coastal motorway near Postojna, with approximately 30 workers relocated from other sites to facilitate the shift. According to Marko Vihtelič from Kolektor CPG, this change could shorten the project timeline by 20–30 days. The possibility of night work was already included in the contract, and no additional annexes will be signed. Infrastructure and Energy Minister Jernej Vrtovec stated that efforts to implement night work would also be made at other motorway construction sites.
Bias read (Center): The article presents factual information without overtly biased language or selective sourcing. It reports on infrastructure developments and includes quotes from both officials and contractors without apparent ideological framing.
Official sources cited
- organisation Marko Vihtelič, Kolektor CPG
- government Jernej Vrtovec, Minister for Infrastructure and Energy
24ur (POP TV)IndependentCenter13 days ago A little after 9:00 p.m. the engine stopped on the highway, and the Vrtovec arrived.Minister for Infrastructure and Energy Jernej Vrtovec visited the construction site on the coastal motorway between Ravbar and Postojna, where numerous accidents have caused frustration among drivers. He announced that night work will begin at the site and emphasized that the decision was based on the will to complete the project faster. Vrtovec stated that night work would reduce the completion time by approximately 20 to 30 days, leading to fewer traffic accidents and smoother traffic flow.
Bias read (Center): The article reports on infrastructure development and public statements from a minister without taking a clear ideological stance. It presents factual information and quotes from officials without evident bias or loaded language.
Official sources cited
- government Minister for Infrastructure and Energy Jernej Vrtovec