Bane Nor has been awarded 181.5 million Norwegian kroner by Oslo District Court in a legal dispute with Spanish-Italian contractor AGJV regarding issues with the Follobanen rail line, including train disruptions and water leaks since its opening in 2022. The court also ordered AGJV to cover Bane Nor's legal costs of 33.7 million kroner. Initially, AGJV had claimed 163 million kroner, while Bane Nor had counterclaimed 480 million kroner. The case, which began in September of last year, was partially settled in December, reducing the scope of the dispute.