The tunnel section of Madrid's A-5 motorway underground project is scheduled to be completed by late Thursday night, allowing traffic to begin using it on December 23. Borja Carabante, the city delegate for Urbanism, Environment, and Mobility, announced that the final eight beams will be installed during the early hours of Thursday to connect the A-5 tunnels with the M-30 ring road. Since the A-5 was fully closed on November 10, a team of 400 workers has been installing 128 beams, each 30 meters long, covering the 172-meter gap between the two tunnel systems. This milestone completes the physical connection required for the first vehicles to traverse the new infrastructure.