The article discusses the slow progress in using funds allocated for preventing landslides and floods in Italy, highlighting the case of Niscemi where a rock fracture revealed administrative paralysis. Despite new funding approved by Prime Minister Giorgia Meloni and efforts by the head of Civil Protection, only 41% of the total allocated funds have been spent, leaving over 1.9 billion euros unused. The Court of Auditors' report highlights widespread issues with delayed implementation of projects, with many initiatives stalled for years due to unclear responsibilities and bureaucratic inefficiencies. Over 5,400 projects were examined, showing that nearly 60% of them had been initiated between 2018 and 2022 but remain incomplete.